Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

A.
Collect Requirements
A.
Collect Requirements
Answers
B.
Direct and Manage Project Execution
B.
Direct and Manage Project Execution
Answers
C.
Monitor and Control Project Work
C.
Monitor and Control Project Work
Answers
D.
Develop Project Management Plan
D.
Develop Project Management Plan
Answers
Suggested answer: D

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.
Initiating
A.
Initiating
Answers
B.
Monitoring and Controlling
B.
Monitoring and Controlling
Answers
C.
Planning
C.
Planning
Answers
D.
Closing
D.
Closing
Answers
Suggested answer: C

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?

A.
-700
A.
-700
Answers
B.
-200
B.
-200
Answers
C.
200
C.
200
Answers
D.
500
D.
500
Answers
Suggested answer: A

Which type of managers do composite organizations involve?

A.
Functional managers and manager of project managers
A.
Functional managers and manager of project managers
Answers
B.
Functional managers only
B.
Functional managers only
Answers
C.
Project managers only
C.
Project managers only
Answers
D.
Technical managers and project managers
D.
Technical managers and project managers
Answers
Suggested answer: A

Assigned risk ratings are based upon:

A.
Root cause analysis.
A.
Root cause analysis.
Answers
B.
Risk probability and impact assessment.
B.
Risk probability and impact assessment.
Answers
C.
Expert judgment.
C.
Expert judgment.
Answers
D.
Revised stakeholders' tolerances.
D.
Revised stakeholders' tolerances.
Answers
Suggested answer: B

Which tool is used to develop technical details within the project management plan?

A.
Expert judgment
A.
Expert judgment
Answers
B.
Project management methodology
B.
Project management methodology
Answers
C.
Project management information system (PMIS)
C.
Project management information system (PMIS)
Answers
D.
Project selection methods
D.
Project selection methods
Answers
Suggested answer: A

What is the name of a graphic display of project team members and their reporting relationships?

A.
Role dependencies chart
A.
Role dependencies chart
Answers
B.
Reporting flow diagram
B.
Reporting flow diagram
Answers
C.
Project organization chart
C.
Project organization chart
Answers
D.
Project team structure diagram
D.
Project team structure diagram
Answers
Suggested answer: C

Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?

A.
Scope plan
A.
Scope plan
Answers
B.
Product scope
B.
Product scope
Answers
C.
Scope management plan
C.
Scope management plan
Answers
D.
Scope baseline
D.
Scope baseline
Answers
Suggested answer: D

What type of reward can hurt team cohesiveness?

A.
Sole-sum
A.
Sole-sum
Answers
B.
Win-lose
B.
Win-lose
Answers
C.
Lose-win
C.
Lose-win
Answers
D.
Partial-sum
D.
Partial-sum
Answers
Suggested answer: B

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.
Finish-to-start planning
A.
Finish-to-start planning
Answers
B.
Rolling wave planning
B.
Rolling wave planning
Answers
C.
Short term planning
C.
Short term planning
Answers
D.
Dependency determination
D.
Dependency determination
Answers
Suggested answer: B