A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

A.
Reactionary risks
A.
Reactionary risks
Answers
B.
Chain risks
B.
Chain risks
Answers
C.
Secondary risks
C.
Secondary risks
Answers
D.
In flux risks
D.
In flux risks
Answers
Suggested answer: C

You are the program manager for your organization. You have proposed a program that will cost $750,000 and will last for four years. Management is concerned with the cost of the program in relation to the return your program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?

A.
$750,000
A.
$750,000
Answers
B.
$795,000
B.
$795,000
Answers
C.
$750,001
C.
$750,001
Answers
D.
$946,857
D.
$946,857
Answers
Suggested answer: D

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

A.
Analogous estimating
A.
Analogous estimating
Answers
B.
Organizational process assets
B.
Organizational process assets
Answers
C.
Parametric scope definition
C.
Parametric scope definition
Answers
D.
Template driven
D.
Template driven
Answers
Suggested answer: D

What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?

A.
Run chart
A.
Run chart
Answers
B.
Scatter diagram
B.
Scatter diagram
Answers
C.
Control chart
C.
Control chart
Answers
D.
Pareto diagram
D.
Pareto diagram
Answers
Suggested answer: B

All of the following are resources that need to be monitored and controlled except for which one?

A.
Equipment
A.
Equipment
Answers
B.
Staff
B.
Staff
Answers
C.
Quality
C.
Quality
Answers
D.
Facilities
D.
Facilities
Answers
Suggested answer: C

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

A.
pert
A.
pert
Answers
B.
gert
B.
gert
Answers
C.
pmis
C.
pmis
Answers
D.
Monte Carlo
D.
Monte Carlo
Answers
Suggested answer: D

All of the following are resources that you will need to monitor and control in a program environment except for which one?

A.
Staff members
A.
Staff members
Answers
B.
Contracts
B.
Contracts
Answers
C.
Quality
C.
Quality
Answers
D.
Equipment
D.
Equipment
Answers
Suggested answer: B

You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

A.
The local government
A.
The local government
Answers
B.
The change control board
B.
The change control board
Answers
C.
The stakeholders
C.
The stakeholders
Answers
D.
The program board
D.
The program board
Answers
Suggested answer: D

What cost estimating approach uses the work breakdown structure to create a cost estimate?

A.
Analogous
A.
Analogous
Answers
B.
Definitive
B.
Definitive
Answers
C.
Top down
C.
Top down
Answers
D.
Parametric
D.
Parametric
Answers
Suggested answer: B

Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

A.
Quality control is a management-driven effort to plan the work properly so the work is done according to plan.
A.
Quality control is a management-driven effort to plan the work properly so the work is done according to plan.
Answers
B.
Quality control is an inspection-driven process to keep mistakes out of the customers' hands.
B.
Quality control is an inspection-driven process to keep mistakes out of the customers' hands.
Answers
C.
Quality control is a management-driven policy to do the work correctly the first time.
C.
Quality control is a management-driven policy to do the work correctly the first time.
Answers
D.
Quality control is an inspection-driven process to prove the existence of the requirements.
D.
Quality control is an inspection-driven process to prove the existence of the requirements.
Answers
Suggested answer: B
Total 451 questions
Go to page: of 46