PMI PgMP Practice Test - Questions Answers, Page 13
List of questions
Related questions
You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?
You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?
You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?
You are the program manager of a new program in your organization. This program will last for one year and your program team will work full-time on the effort.
The nature of the work requires that the program team work closely together for the next year, but many of the program team members have never met one another. You decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?
A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?
Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?
Which one of the following is the best example of transference?
You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule performance index (SPI) for this program?
You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?
You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?
Question