PMI PgMP Practice Test - Questions Answers, Page 12

List of questions
Question 111

Which project management meeting allows stakeholders to meet one another and to learn about the project?
Question 112

You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?
Question 113

Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?
Question 114

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
Question 115

Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?
Question 116

Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.
Question 117

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?
Question 118

In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?
Question 119

You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?
Question 120

Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?
Question