Which project management meeting allows stakeholders to meet one another and to learn about the project?

A.
Project scope review
A.
Project scope review
Answers
B.
Project authorization meeting
B.
Project authorization meeting
Answers
C.
Project status meeting
C.
Project status meeting
Answers
D.
Project kick-off meeting
D.
Project kick-off meeting
Answers
Suggested answer: D

You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?

A.
Life cycle costing estimates
A.
Life cycle costing estimates
Answers
B.
Lessons learned documentation
B.
Lessons learned documentation
Answers
C.
Operational transfer plan
C.
Operational transfer plan
Answers
D.
Program closure reports
D.
Program closure reports
Answers
Suggested answer: D

Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

A.
RFI
A.
RFI
Answers
B.
RFP
B.
RFP
Answers
C.
RFQ
C.
RFQ
Answers
D.
IFB
D.
IFB
Answers
Suggested answer: A

If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

A.
.99
A.
.99
Answers
B.
-$2,500
B.
-$2,500
Answers
C.
$2,500
C.
$2,500
Answers
D.
1.02
D.
1.02
Answers
Suggested answer: C

Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

A.
Net present value
A.
Net present value
Answers
B.
Future value
B.
Future value
Answers
C.
Present value
C.
Present value
Answers
D.
Cost-Benefit ratio
D.
Cost-Benefit ratio
Answers
Suggested answer: A

Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

A.
Half float
A.
Half float
Answers
B.
Full float
B.
Full float
Answers
C.
Total float
C.
Total float
Answers
D.
Free float
D.
Free float
Answers
Suggested answer: C, D

You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

A.
Contract and the quality measurements for the vendor's work
A.
Contract and the quality measurements for the vendor's work
Answers
B.
The scope verification document and the termination notice
B.
The scope verification document and the termination notice
Answers
C.
Contract and scope verification process documents
C.
Contract and scope verification process documents
Answers
D.
Work that has been completed and uncompleted work
D.
Work that has been completed and uncompleted work
Answers
Suggested answer: D

In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

A.
Quality control
A.
Quality control
Answers
B.
Process improvement
B.
Process improvement
Answers
C.
Scope verification
C.
Scope verification
Answers
D.
Quality assurance
D.
Quality assurance
Answers
Suggested answer: D

You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

A.
Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
A.
Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
Answers
B.
With program execution
B.
With program execution
Answers
C.
With program initiation
C.
With program initiation
Answers
D.
With program planning
D.
With program planning
Answers
Suggested answer: A

Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

A.
Operational transfer alliance plan
A.
Operational transfer alliance plan
Answers
B.
Program milestone list
B.
Program milestone list
Answers
C.
Program transition agreement
C.
Program transition agreement
Answers
D.
Program scope statement
D.
Program scope statement
Answers
Suggested answer: C