Molly is the program manager for her organization and she is creating a program plan that defines the benefits of the program and how her program and team will create the benefits for the organization. What plan is Molly creating in this scenario?
Which of the following is NOT true regarding the program work breakdown structure (WBS)?
Program management has several themes that the program manager must be aware of. Which one of the following is not a program management theme?
You are the program manager for your organization. One of the projects within your program is to install 15,000 light fixtures throughout your organization's corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?
Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?
Mary has just completed a large program for her organization. What should Mary now do with the program records that she has created throughout the program?
You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any questions the vendors may have about the project. What is this meeting called?
Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?
Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?
What is the primary purpose of a project kick-off meeting?