Question 181

Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?
Question 182

Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?
Question 183

What is a stakeholder analysis chart?
Question 184

You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?
Question 185

Wanda is the program manager for her organization. Her program team consists of resources from across the organization - many of whom have not worked together before. Wanda thinks that she'll need to complete some team development but would like to focus the development on the materials and activities that the program team will need to complete in the program. What plan should Wanda reference and update to complete her team development process?
Question 186

You have identified several issues in your program and have assigned issue owners. What component of program management oversees issue resolution?
Question 187

You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one?
Question 188

Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?
Question 189

You are the program manager for your organization and are working with your program team to create the program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?
Question 190

Robert is the program manager for his organization which operates in a matrix structure.
Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should
Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?
Question