ExamGecko
Home / PMI / PgMP / List of questions
Ask Question

PMI PgMP Practice Test - Questions Answers, Page 32

Add to Whishlist

List of questions

Question 311

Report Export Collapse

A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the projects, several mandatory changes are identified that would extend the program's completion date.

What is the next step for the program manager?

Become a Premium Member for full access
  Unlock Premium Member

Question 312

Report Export Collapse

During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 313

Report Export Collapse

An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.

What should the program manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 314

Report Export Collapse

The program director of a four-year program, estimated to require 600,000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the test phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation.

Which of the following metrics should the PMO capture on a monthly basis?

Become a Premium Member for full access
  Unlock Premium Member

Question 315

Report Export Collapse

Stakeholders ask the program manager to assess reasons for the project's delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.

The program manager distributes information in accordance with which of the following?

Become a Premium Member for full access
  Unlock Premium Member

Question 316

Report Export Collapse

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.

Based on this information, the program manager determines which of the following?

Become a Premium Member for full access
  Unlock Premium Member

Question 317

Report Export Collapse

A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

Become a Premium Member for full access
  Unlock Premium Member

Question 318

Report Export Collapse

While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?

Become a Premium Member for full access
  Unlock Premium Member

Question 319

Report Export Collapse

A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.

Before, initiating closeout and releasing the resources, what should the program manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 320

Report Export Collapse

A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.

What activity should the program manager perform next?

Become a Premium Member for full access
  Unlock Premium Member
Total 451 questions
Go to page: of 46
Search

Related questions