List of questions
Related questions
Question 1397 - PMP discussion
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?
A.
After full development is completed
B.
When the sponsor approves the increment
C.
When a major feature is completed
D.
At the end of each and every iteration
Your answer: