Question 1398 - PMP discussion
Toward the end of a project, the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
A.
Review the stakeholder engagement plan.
B.
Review the requirements traceability matrix.
C.
Review the quality management plan.
D.
Review the work breakdown structure (WBS).