A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

A.

Assign a qualified team member to be the risk manager for the project.

Answers
A.

Assign a qualified team member to be the risk manager for the project.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

Answers
B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

Answers
C.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Answers
D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Suggested answer: D