A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
A.
Assign a qualified team member to be the risk manager for the project.
B.
Remove the user stories associated to that risk and avoid the impact to the project deliverables.
C.
Submit a change request to transfer the risk to a third party in case it becomes an issue.
D.
Ask the team to monitor the risk and provide an alert if it becomes an issue.