Question 1434 - PMP discussion

Report
Export

A project manager who is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

A.

Qualitative risk analysis

Answers
A.

Qualitative risk analysis

B.

Regression analysis

Answers
B.

Regression analysis

C.

Stakeholder analysis

Answers
C.

Stakeholder analysis

D.

Decision tree analysis

Answers
D.

Decision tree analysis

Suggested answer: C
asked 12/11/2024