Question 1434 - PMP discussion
A project manager who is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.
In what type of analysis should the project manager use this information?
A.
Qualitative risk analysis
B.
Regression analysis
C.
Stakeholder analysis
D.
Decision tree analysis
Your answer: