A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

A.

Check the expert's availability within the organization on an as-needed basis

Answers
A.

Check the expert's availability within the organization on an as-needed basis

B.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment

Answers
B.

Review the project's key performance indicators (KPIs) to determine the impact of this assignment

C.

Ask the project sponsor to assign a new resource with the necessary expertise to the team

Answers
C.

Ask the project sponsor to assign a new resource with the necessary expertise to the team

D.

Develop the team member's capacities through mentoring and training

Answers
D.

Develop the team member's capacities through mentoring and training

Suggested answer: A