Question 1437 - PMP discussion
A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more information to be shared.
What should the project manager do next?
A.
Consult the scope baseline document to track project updates.
B.
Update the project communications management plan immediately.
C.
Inform the stakeholder to wait for the annual stakeholder review meeting.
D.
Schedule a meeting with the stakeholder to better understand their request.