ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1438 - PMP discussion

Report
Export

A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed one of the risks materialized and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?

A.

Risk occurred

Answers
A.

Risk occurred

B.

Risk monitored

Answers
B.

Risk monitored

C.

Risk managed

Answers
C.

Risk managed

D.

Risk identified

Answers
D.

Risk identified

Suggested answer: A
asked 12/11/2024
Cyrom Meryll Santos
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first