Question 1439 - PMP discussion
A project manager works at an organization that is transitioning to agile. The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
A.
Develop a communications management plan for each category in the stakeholder register.
B.
Advise the project management office (PMO) to use the burndown chart as the single communication channel.
C.
Include the burndown chart in a monthly report that is distributed to all stakeholders.
D.
Postpone the recommendation since the organization does not currently have a defined agile methodology.