A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests. Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders.

What document should the project manager use to communicate these requests?

A.

Risk log

Answers
A.

Risk log

B.

Backlog

Answers
B.

Backlog

C.

Change log

Answers
C.

Change log

D.

Issue log

Answers
D.

Issue log

Suggested answer: C