A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.

What should the project manager do to avoid these situations?

A.
Review the stakeholder engagement plan.
Answers
A.
Review the stakeholder engagement plan.
B.
Review the resource management plan.
Answers
B.
Review the resource management plan.
C.
Review the risk management plan.
Answers
C.
Review the risk management plan.
D.
Review the communications management plan.
Answers
D.
Review the communications management plan.
Suggested answer: D