A project team is conducting sprint planning. At the end of the sprint, the product increment must be deployed on a customer's site. The product owner received an email from the account manager that the customer may not be ready to install the new version of the product.

What should the project manager do?

A.
Ask the sales team to inform the customer.
Answers
A.
Ask the sales team to inform the customer.
B.
Contact the customer's project manager.
Answers
B.
Contact the customer's project manager.
C.
Ask the product owner to inform the customer.
Answers
C.
Ask the product owner to inform the customer.
D.
Contact the customer's technical lead.
Answers
D.
Contact the customer's technical lead.
Suggested answer: B