PMI PMP Practice Test - Questions Answers, Page 27

List of questions
Question 261

A project manager discovers that the project team is spending a large amount of time delivering several reporting formats for the same project updates to multiple stakeholders.
What should the project manager do to reduce the time spent on these activities?
Question 262

A project manager has been transferred to another country to work on a key project. The project manager successfully completed the planning phase and has started the execution phase, reporting good progress. During the last meeting with the project sponsor, the project manager was told that some stakeholders have complained that the project manager's emails are very harsh.
What should the project manager do to solve this situation?
Question 263

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined.
What should the project manager do?
Question 264

A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.
Which approach should the project manager use as a servant leader?
Question 265

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.
What should the project manager do in this situation?
The project manager should first try to establish virtual teams for meetings and deliverables as an alternative to face-to-face meetings. This will ensure that the team can still communicate and collaborate effectively.
Explanation:
Question 266

A key project stakeholder does not attend any of the project meetings and is providing false information that the project team is not delivering on time.
What should the project manager do to address this situation?
Question 267

A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring so many iterations with a risk of not reaching the mandatory delivery date.
Which approach should the project manager use in this situation?
Question 268

A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.
What should the project manager establish first in the project governance structure?
The project manager should first establish a clear RACI matrix in the project governance structure. The RACI matrix defines the roles and responsibilities of each team member, outlining who is responsible for making decisions, who is accountable for the outcomes, who should be consulted, and who should be informed. This will help to ensure that there is a clear understanding of who is responsible for assigning tasks and managing work assignments. This will help to prevent confusion and conflicts among team members, and ensure that the team is able to work effectively.
Explanation:
Question 269

A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses.
The project manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?
Question 270

A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?
Question