PMI PMP Practice Test - Questions Answers, Page 28

List of questions
Question 271

During project implementation, one team finds out that a key project deliverable was not budgeted.
What should the project manager do first?
Question 272

During the final stage of the launch for a new design, team members are having a conflict about some features of the design.
What should the project manager do?
Question 273

An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.
What should the project manager do?
Question 274

Key decision makers are meeting to define the objectives of a new database migration project.
There are many disagreements about scope and time lines among the leaders of various company departments.
How should the project manager impartially prioritize the requirements to be integrated?
Question 275

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer.
What guidance should the product manager provide to improve the requirement development?
Question 276

A project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
Question 277

A government agency is developing a new connectivity policy. The assigned project manager is a famous economist with international recognition. The team is eager to work with the project manager, but feels intimidated. The project manager realizes that a junior economist, whose tasks are behind schedule, is especially intimidated by the situation.
What should the project manager do first?
Question 278

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?
Question 279

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.
What should the project manager do next?
Question 280

An organization is transitioning from a predictive to an agile approach.
What should the project manager do to ensure that the agile approaches will bring about significant change?
Question