PMI PMP Practice Test - Questions Answers, Page 30
List of questions
Related questions
In a software development project, the product owner and development team agree on a sprint backlog. The highest priority in the backlog is to build a payment module. The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines.
At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
During an ongoing project, a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy.
What should the project manager share with the key resource?
After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run.
What two actions should the project manager take? (Choose two.)
A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The design is already approved.
What should be the project manager's next steps?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI).
What should the project manager do?
After the project charter's approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders.
However, not all of the stakeholders are immediately available for a meeting in the short term.
What should the project manager do in order to gather the information needed from stakeholders?
A project manager has been selected to deliver one of an organization's key flagship solutions.
Critical success factors include agility, market adaptation, and a quick response to market offerings.
What is one of the key activities that the project manager should undertake to ensure company success?
During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
During a project's third iteration, two of the existing team members were replaced. As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?
Question