ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 31

Add to Whishlist

List of questions

Question 301

Report Export Collapse

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined. The actual invoice payments received have also been late and were outside of the contracted payment schedule.

Recent invoices have only been partially paid.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 302

Report Export Collapse

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams.

As a team facilitator, what should the project manager do to avoid this?

Become a Premium Member for full access
  Unlock Premium Member

Question 303

Report Export Collapse

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

Become a Premium Member for full access
  Unlock Premium Member

Question 304

Report Export Collapse

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?

Become a Premium Member for full access
  Unlock Premium Member

Question 305

Report Export Collapse

A company is changing their current business model. The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three.)

Become a Premium Member for full access
  Unlock Premium Member

Question 306

Report Export Collapse

A new resource has joined an iterative project team. The project manager notices that the resource is unable to complete the deliverables on time.

How should the project manager address this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 307

Report Export Collapse

A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?

Become a Premium Member for full access
  Unlock Premium Member

Question 308

Report Export Collapse

A transportation company is transforming its operational processes and the main system this company uses to move freight. The scope statement is in place. An iterative delivery approach has been agreed by all stakeholders.

What does the project manager need to do next to help the team understand the work that needs to be done?

Become a Premium Member for full access
  Unlock Premium Member

Question 309

Report Export Collapse

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined. The project manager is also informed that the key stakeholder does not want to hold a working session.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 310

Report Export Collapse

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months.

What should the project lead do next?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions