PMI PMP Practice Test - Questions Answers, Page 33
List of questions
Related questions
The following table shows the business value created and the development effort required to implement various features in a product.
Which feature should the team prioritize first? Enter the feature name in the box below. ______
An agile project is running activities to define the minimum viable product (MVP). During the session, the project manager identifies some mandatory regulations, but there is no consensus to include these regulations in the MVP because it may extend the duration of the project.
What should the project manager do?
A project team has recently completed the initial sprint for developing an automated payroll system for a company. The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next.
Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two.)
A project manager is responsible for building a bridge. The high-level elements of the project are handled using a predictive approach. The software responsible for retracting the bridge has been developed based on agile principles. During software development, the workflow is often interrupted by various delays or impediments due to lack of information.
How should the project manager handle this situation?
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources.
What should the project manager do next?
A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results.
Which tool or technique should the project manager use?
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project.
What should the project manager do to enhance the success of the project?
During the course of the project, several obstacles are identified that are preventing the project from moving forward.
What should the project manager do to remove the obstacles?
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned.
What two actions can the project manager take to be more cost effective? (Choose two.)
A project manager is working with a Scrum team that is continually missing deadlines. The steering committee is concerned about the project as it is not clear that it will deliver the expected value. After some analysis, the project manager discovers there is a mismatch of competencies in one of the teams.
What should the project manager do?
Question