PMI PMP Practice Test - Questions Answers, Page 32
List of questions
Related questions
A new project manager is assigned to lead an agile project. The project manager wants to use motivation to encourage the team to perform well throughout the project.
What should the project manager do?
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low- level risks remain.
What should the project manager do now?
A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.
How should the project manager respond?
The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?
A research and development team is finishing up a two year initiative. The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
An agile project team is looking to develop quality standards for a project.
How should the project manager coach the team?
Due to delays on some activities, one of the project team members has increased the scope without any approval.
What should the project manager do next?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations. The project does not pass the financial threshold but is also expected to increase market share, improve customer services, and retain more customers. The project is planned as a phased implementation, building on learning from the retrospectives during each phase.
How should the business increase the value of the project?
During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?
Question