Question 241
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In the middle of the execution phase for a big project, a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress.
What should the project manager do first?
Explanation:
When a new stakeholder joins the board of directors and is impacting the project's progress, it's crucial for the project manager to ensure that the stakeholder is fully informed about the project, its objectives, and its current status. By presenting the project to the stakeholder, the project manager can ensure that the stakeholder is aware of the project's goals, timelines, and deliverables, and that they understand the impact that their decisions may have on the project.
This will help the project manager to manage the stakeholder's expectations and ensure that their influence on the project is aligned with the project's goals.
Explanation:
Question 242
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment.
What type of analysis should the project lead have conducted to avoid this situation?
Question 243
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team.
What should the project manager verify first?
Question 244
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
Question 245
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.
How should the project manager address the issue?
Question 246
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed.
Which two actions should the project manager take? (Choose two.)
Explanation:
The project manager should first ask the customer for their priorities regarding the requirements for the second milestone in order to understand the reasons behind the customer's request and how it aligns with their overall project goals.
This can help the project manager to identify which requirements are most important to the customer and which ones can be delayed or modified.
The project manager should also go back to the development team and discuss which second milestone requirements can be performed in the first quarter. The team may be able to identify which requirements can be accelerated or modified to meet the customer's desired outcome in the first quarter. This can help the project manager to develop a plan that meets the customer's needs while minimizing the impact on the overall project schedule and cost.
Explanation:
Question 247
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project team is conducting sprint planning. At the end of the sprint, the product increment must be deployed on a customer's site. The product owner received an email from the account manager that the customer may not be ready to install the new version of the product.
What should the project manager do?
Question 248
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
Question 249
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During a sprint, one of the team members found an issue. According to the team member and the product owner, the issue has a higher level of importance than the other features of the sprint, but is not a roadblock to completing it.
What should the project lead ask the project team do?
Question 250
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external resource because of the high cost, even though it is within the project budget.
What should the project manager do to resolve this issue?
Question