Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects.

How should a project manager solve this issue?

A.
Propose implementing a new project management information system (PMIS).
Answers
A.
Propose implementing a new project management information system (PMIS).
B.
Request a meeting with senior management to escalate the situation
Answers
B.
Request a meeting with senior management to escalate the situation
C.
Promote adoption of the communications management plan with the project team.
Answers
C.
Promote adoption of the communications management plan with the project team.
D.
Host a team-building event to develop team cohesion and improve communication
Answers
D.
Host a team-building event to develop team cohesion and improve communication
Suggested answer: C