Question 443 - PMP discussion
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing.
What should the project manager do?
A.
Conduct an expert judgment evaluation.
B.
Review the quality management plan
C.
Update the lessons learned register
D.
Review the risk management plan
Your answer: