Question 444 - PMP discussion
A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished.
How should the project manager approach this situation?
A.
Request that the customer reviews and clarifies feature definitions for the current sprint
B.
Send a burndown chart of the current sprint to the customer and seek clarifications.
C.
Educate the customer and have them participate in daily standup meetings.
D.
Schedule weekly meetings and product reviews with the customer to clarify requirements
Your answer: