A project manager has received an updated earned value analysis report. The following are the key findings from the report:

*Budget at completion = US$1 million

*Earned value = US$0,7 million

*Actual cost = US$0,75 million

*Cost performance index = 0,933

Based on this information, what should the project manager conclude about project performance?

A.
The project will be completed exactly as planned
Answers
A.
The project will be completed exactly as planned
B.
The project will be easier to complete than planned
Answers
B.
The project will be easier to complete than planned
C.
The project will be difficult to complete as planned
Answers
C.
The project will be difficult to complete as planned
D.
The project will not be completed as planned
Answers
D.
The project will not be completed as planned
Suggested answer: C