Question 446 - PMP discussion

Report
Export

A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data. Some external stakeholders are reluctant to provide support.

What approach should the project manager take?

A.
Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project
Answers
A.
Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project
B.
Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
Answers
B.
Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
C.
Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk
Answers
C.
Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk
D.
Host a project team meeting, then update the risk register and the project management plan
Answers
D.
Host a project team meeting, then update the risk register and the project management plan
Suggested answer: B