A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

A.
Analyze both projects to determine the most effective use of common resources
Answers
A.
Analyze both projects to determine the most effective use of common resources
B.
Use resource optimization to justify requesting more resources for the critical project
Answers
B.
Use resource optimization to justify requesting more resources for the critical project
C.
Provide schedule optimization training to the project teams to improve their skills
Answers
C.
Provide schedule optimization training to the project teams to improve their skills
D.
Apply fast-tracking techniques to compress the schedule of the critical project
Answers
D.
Apply fast-tracking techniques to compress the schedule of the critical project
Suggested answer: A