A project manager for a maintenance project has a contract that is renewed annually. The project started 6 years ago. After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year.

What has happened in this situation?

A.
The contract has not been appropriately reviewed by the project team
Answers
A.
The contract has not been appropriately reviewed by the project team
B.
The stakeholder engagement plan has not been correctly implemented
Answers
B.
The stakeholder engagement plan has not been correctly implemented
C.
The legal department has not disseminated the law correctly to all staff
Answers
C.
The legal department has not disseminated the law correctly to all staff
D.
The project manager does not have enough knowledge on this legal matter
Answers
D.
The project manager does not have enough knowledge on this legal matter
Suggested answer: C