Question 464 - PMP discussion

Report
Export

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization. After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status.

What should the project manager do?

A.
Update the stakeholder engagement assessment matrix
Answers
A.
Update the stakeholder engagement assessment matrix
B.
Update the communications management plan to include informal requests
Answers
B.
Update the communications management plan to include informal requests
C.
Ask the team member to develop a dashboard to fulfill the request
Answers
C.
Ask the team member to develop a dashboard to fulfill the request
D.
Tell the team member to route the request through the project manager
Answers
D.
Tell the team member to route the request through the project manager
Suggested answer: B