Question 467 - PMP discussion

Report
Export

A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.

What should the project manager do?

A.
Wait for the team to identify and solve the problem independently
Answers
A.
Wait for the team to identify and solve the problem independently
B.
Move the team member to another task that is more skill appropriate
Answers
B.
Move the team member to another task that is more skill appropriate
C.
Have a confidential discussion with the team member to identify the root cause
Answers
C.
Have a confidential discussion with the team member to identify the root cause
D.
Start a discussion with all team members to help resolve the issues
Answers
D.
Start a discussion with all team members to help resolve the issues
Suggested answer: C