Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule.
How should the project manager address this situation?
A.
Meet with the project team to decide how the remaining budget will be spent
B.
Keep the extra budget as management reserve until project closeout
C.
Give the team extra time to finish tasks within the original timeline
D.
Follow the project escalation policy and communications management plan