List of questions
Related questions
Question 471 - PMP discussion
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
A.
Set up a meeting with key stakeholders to clarify requirements
B.
Escalate to the project steering committee and request additional time
C.
Travel to the development team's office to push the schedule
D.
Create prototypes with the development team to confirm requirements
Your answer:
0 comments
Sorted by
Leave a comment first