The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies.

What should the project manager do?

A.
Make sure the project team is aware of all agile techniques
Answers
A.
Make sure the project team is aware of all agile techniques
B.
Skip the training because the team already understands agile
Answers
B.
Skip the training because the team already understands agile
C.
Ensure the team has a common understanding of agile
Answers
C.
Ensure the team has a common understanding of agile
D.
Teach one agile methodology fully and completely
Answers
D.
Teach one agile methodology fully and completely
Suggested answer: C