Question 492 - PMP discussion
For the purposes of quality assurance, a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available.
Why is an attendance list important?
A.
It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance
B.
The attendance list is evidence that risk review meetings were held with the appropriate project team members
C.
It is a record that shows the number of attendees in the meeting
D.
It is a document that is registered within the lessons learned register
Your answer: