Question 493 - PMP discussion

Report
Export

A company is initiating a project to enhance one of its existing products. All of its products are developed internally.

What should the project manager do?

A.
Ensure the stakeholder engagement plan is accurate and properly documented
Answers
A.
Ensure the stakeholder engagement plan is accurate and properly documented
B.
Review the lessons learned from the previous project
Answers
B.
Review the lessons learned from the previous project
C.
Identify the risk of implementing the new solution and evaluate the impact on the project
Answers
C.
Identify the risk of implementing the new solution and evaluate the impact on the project
D.
Create a lessons learned document for the initiation phase
Answers
D.
Create a lessons learned document for the initiation phase
Suggested answer: B