Question 496 - PMP discussion

Report
Export

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

A.
Ensured that all defects identified during testing were resolved before implementation
Answers
A.
Ensured that all defects identified during testing were resolved before implementation
B.
Ensured that all of the required tasks identified in the scope were completed successfully
Answers
B.
Ensured that all of the required tasks identified in the scope were completed successfully
C.
Ensured that all documentation was completed post implementation before closing the project
Answers
C.
Ensured that all documentation was completed post implementation before closing the project
D.
Ensured that all the required approvals were received per the organizational procedures
Answers
D.
Ensured that all the required approvals were received per the organizational procedures
Suggested answer: D
asked 23/09/2024
Hendrik Woldhuis
50 questions