A project team is executing a megaproject, and several contract requirements have been identified.

In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.

What should project manager do?

A.
Seek management's approval for executing the contract earlier than planned.
Answers
A.
Seek management's approval for executing the contract earlier than planned.
B.
Request the team to initiate a change request to execute the contract.
Answers
B.
Request the team to initiate a change request to execute the contract.
C.
Support the team's request and allow for early contract execution.
Answers
C.
Support the team's request and allow for early contract execution.
D.
Challenge the project team to identify the reasons for early contract execution.
Answers
D.
Challenge the project team to identify the reasons for early contract execution.
Suggested answer: B