A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document and include it in the lessons learned register.

What should the project manager do?

A.
Assign the documenting task to a project team member.
Answers
A.
Assign the documenting task to a project team member.
B.
Ask the SME to document and capture the occurrence.
Answers
B.
Ask the SME to document and capture the occurrence.
C.
Request the SME to wait until the project closure phase.
Answers
C.
Request the SME to wait until the project closure phase.
D.
Take ownership of documenting this information.
Answers
D.
Take ownership of documenting this information.
Suggested answer: D