Question 548 - PMP discussion
During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.
What should the project manager pay special attention to in order to achieve this goal?
A.
Reviewing and updating the requirements management plan
B.
Carrying out quality audits and failure analyses
C.
Monitoring the work breakdown structure (WBS)
D.
Monitoring and updating the benefits realization plan
Your answer: