Question 553 - PMP discussion

Report
Export

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.

What approach should be used in this situation?

A.
The team facilitator gets support from external team members.
Answers
A.
The team facilitator gets support from external team members.
B.
The team members bring in a specialist to help them
Answers
B.
The team members bring in a specialist to help them
C.
The product owner moves it to the product backlog.
Answers
C.
The product owner moves it to the product backlog.
D.
The cross-functional team member work together to complete the activity
Answers
D.
The cross-functional team member work together to complete the activity
Suggested answer: D
asked 23/09/2024
Alexis Chacon
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first