A multinational company has a plan to expand their business into a new country where they currently have no presence. A project manager is assigned to initiate this project.

After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

A.
Acquire project resources from the new country to mitigate the risk of uncertainty
Answers
A.
Acquire project resources from the new country to mitigate the risk of uncertainty
B.
Evaluate the environmental and regulatory factors and identify high-level risks and assumptions
Answers
B.
Evaluate the environmental and regulatory factors and identify high-level risks and assumptions
C.
Identify and monitor the risks closely since the company does not have lessons learned for this country
Answers
C.
Identify and monitor the risks closely since the company does not have lessons learned for this country
D.
Ensure that project sponsors are in agreement on the project deliverables and timeline during the project
Answers
D.
Ensure that project sponsors are in agreement on the project deliverables and timeline during the project
Suggested answer: B