A project manager is leading a large-scale project that involves 70 stakeholders. The project manager has heard various comments and expectations from the customers, some of which are contradictory. Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

A.
Escalate the issue to the management team for their review and guidance
Answers
A.
Escalate the issue to the management team for their review and guidance
B.
Create a survey template to collect feedback from stakeholders to reach an agreement
Answers
B.
Create a survey template to collect feedback from stakeholders to reach an agreement
C.
Organize a face-to-face meeting with all stakeholders to understand their interests and concerns
Answers
C.
Organize a face-to-face meeting with all stakeholders to understand their interests and concerns
D.
Leverage expert judgment to determine the requirements that should be considered
Answers
D.
Leverage expert judgment to determine the requirements that should be considered
Suggested answer: C