Question 561 - PMP discussion
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project.
What should the project manager do first to determine a governance approach for the project?
A.
Consult a subject matter expert (SME) as to the best governance policies, procedures, and guidelines to be used by the project
B.
Consult with team members and stakeholders to determine whether the organization has any informal governance policies procedures, and guidelines
C.
Choose either a predictive or agile framework best suited to the nature of the project, and use this framework as the basis for project governance policies, procedures, and guidelines
D.
Coach the self-managing team to produce tailored governance policies, procedures and guidelines for the project
Your answer: