Question 565 - PMP discussion

Report
Export

A distributed protect team wants to use the common ground principle to ensure that they have a common understanding of the scope. The team asks the protect lead to set up a workshop.

What should the project lead do?

A.
Ask the senior members of the development team to elaborate on the scope in detail
Answers
A.
Ask the senior members of the development team to elaborate on the scope in detail
B.
Invite participants to the workshop with sufficient lead time to prepare
Answers
B.
Invite participants to the workshop with sufficient lead time to prepare
C.
Reduce the number of participants to ensure that consensus is reached easier
Answers
C.
Reduce the number of participants to ensure that consensus is reached easier
D.
Provide the participants with specific instructions and sot the expectations
Answers
D.
Provide the participants with specific instructions and sot the expectations
Suggested answer: D