List of questions
Related questions
Question 566 - PMP discussion
A client mentioned that in the past 2 months, they have not been invoiced for completed work.
The client has communicated that they will release the funds for other activities it the invoices are not sent.
What should the project manager do next?
A.
Work with the client and agree on a schedule to provide them with the invoices
B.
Reach out to the billing team and instruct them to issue the invoices immediately
C.
Review the previous billing information and prepare a corrective action plan
D.
Communicate and inform the client to go ahead and release the funds
Your answer:
0 comments
Sorted by
Leave a comment first