A critical deliverable for the current iteration is giving the team difficulties. Functionality and quality issues are constantly emerging and delaying iteration progress.

The project manager listens to the team's concerns and discovered that the work is not being well coordinated among the team members.

Which two actions should the project manager take to handle this situation? (Choose two.)

A.
Develop a team performance report to discuss in the next retrospective meeting.
Answers
A.
Develop a team performance report to discuss in the next retrospective meeting.
B.
Provide dear instructions on how the work should flow among the team members.
Answers
B.
Provide dear instructions on how the work should flow among the team members.
C.
Schedule an iteration backlog refinement meeting to understand the issues.
Answers
C.
Schedule an iteration backlog refinement meeting to understand the issues.
D.
Set up one-on-one meetings to provide feedback to the team members.
Answers
D.
Set up one-on-one meetings to provide feedback to the team members.
E.
Prioritize the issues, focusing on the ones affecting the iteration goal.
Answers
E.
Prioritize the issues, focusing on the ones affecting the iteration goal.